Description
PERSONAL DETAIL
Name: Saravanan Elumalai -PMP
DOB: 09th April,1984 (38 Yrs. old)
Marital Status: Married; No. of Children: 2 daughters; 7 Yrs. & 5 Yrs. old
Nationality: Indian
Visa Status: Engineer -Residential Visa Valid until 29th July,2023; Transferable with NOC
CONTACT DETAIL
Address: Zone 91, Al Meshaf,, Qatar,
Mobile: 00974-55183390
Email ID: [email protected] ;
TECHNICAL & PROFESSIONAL QUALIFICATION:
Description of Certification & Qualification
Year of completion
Institution / University
Percentage/Grade
MMUPDA License (Mechanical)
License No. 23685 Valid till 14th Jan, 2026
Jan, 2020
Qatar Ministry
-
Bachelor of Engineering (BE) - Mechanical
June 2002 – May 2006
Anna University, Chennai
76%
MBA in Project Management Specialization
Jan 2010-Sep 2013
Sikkim Manipal
“B” Grade
XII Std.
2002
State Board
82.83%
X Std.
2000
State Board
80.80%
Project Management Professional (PMP Certificate No. 1820900)
Valid Till 8th June,2024
June 2015
Project Management Institute, USA
-
SKILLS
Project Management -Project Design & Technical Management - Time Management - Leadership - Technical Expertise -Problem Solving – Procurement - Expediting - Change/Variations Management - Quality & HSE Management - Sub Contracting Management – Leadership
PROFESSIONAL & HSE TRAININGS/COURSES
- HSE mandatory courses of Qatar Chemicals Company (Q-Chem)
- HSE Mandatory courses of Petroleum Development of Oman (PDO), Occidental Petroleum & QP - High Sour H2S, Initial fire responses, Safety Awareness & Leadership
- PMBOK Training for Project Management Professionals, Chicago, Sharjah, (One of the PMI Recognized REP)
- Project Management Work Shop (5-day Work Shop in Arabian Industries Projects LLC)
EMPLOYEER- PROJECT DETAILS - ROLES & RESPONSIBLITIES
1. Hiap Seng Manco WLL; (Doha-Qatar): Nov 2020 to till Date -Position: Senior Project Manager
Project: Engineering, Procurement, Pre-Fabrication, Erection, Testing, calibration, Painting of 14 nos. low pressure storage tanks (API 620) of various sizes for Qatar Energy- DPFU Project. Scope includes, Sizing of the tanks, Basic and details Design of Equipment; Materials procurement (NACE/ Sour Service EN10204-Type 3.2 certifications) including Steel plates, internals Piping (Super Duplex Stainless Steel), CS Piping materials, accessories procurement & securing materials approvals, hydraulic Jet Mixers system (CFD), PVRV sizing, Provisions for Internal & External Cathodic Protection System, Provisions for earthing connections, Still well designs, accessories such as Stair, ladders, operating platforms - Hydro static, pressure & Vacuum Testing’s of equipment.
Key Tasks and Responsibilities (but not limited to):
- Responsible for Review & validation of all engineering inputs such as data sheets (process & Mechanical), NODs, Project Specifications,
- Providing / coordinating complete mechanical design of the equipment including local load analysis for all nozzles, Pipe, Structural supports, foundation load data, Anchor Bolt design, wind & seismic design etc.,
- Defining raw materials specifications (Purchase requisitions) ensuring all materials/equipment supplied meeting the requirement specified in the data sheets, Project specification, Qatar Energy Standard QP-STD-R001 & NACE-MR0175
- Resolving all engineering queries relating to the equipment
- Review & Submission of all engineering deliverables as per the scope of works for consultant / client review
- Representing / coordinating/ leading all technical meetings & resolving the technical concerns and issues
- Review/ submissions & securing approvals for all technical deliverables, such as calculations, GADs & details designs.
- Responsible for ensuring adequate responses to all technical queries including engineering, procurement or Site related Coordinating and resolving the engineering issue between various stake holders. Developing the system to centralize all interface queries from the all the team and the same to make accessible to all the stakeholders to achieve project goals along with HSE requirements.
- Managing all stakeholders (Internal/External) for Engineering, Procurement, Contracting and construction and able to anticipate and highlight issues/constraints and mitigate. Including Interaction with Management / Vendors / Site Team / commissioning / client team / TPI and resolve all technical issues.
- Review, Submission & securing approvals for Project Construction Procedure, Specification, Construction Execution Plans, Method of Statements, Engineering & Construction Deliverables Reviews, Quality Plans, JHAs for the Safe & efficient execution of project activities.
- Preparation and securing approvals for Technical Deviations & Engineering Queries as necessarily required.
- To prepare/ review / finalize Project Sub-contract Scope / Packages, Basis of Design, Project Execution Plan, Project Schedule, Project Quality Plan, Functional System Specifications, Statement of Requirements, Equipment Data Sheets, Factory Acceptance Testing, Material Take-Off’s, Vendor Document Manuals to the As-built Documents.
- Planning and scheduling for Engineering, Procurement and Construction activities (S-Curves), Budgeting-Cash Inflow-outflow, Mechanical Completion documentation, Consolidation, tracking & liquidation of Punch list from Installation, PSSR, pre-commissioning & Commissioning stages,
- Management of Safety Health and Environmental (SHE) & Tool box talk, ensuring the SHE compliance policies, Identify areas of unsafe work practices/condition. Actively engaged to achieve the Zero Harm ambition across the Project.
- Managing the project planning with priority and sequences along with allocation of manpower and materials. Proven capabilities of interfacing/interacting with all stakeholders including licensors, customer, statutory authorities and vendors on all aspects of project execution. Interfaces between engineering, procurement, contracting and construction and able to anticipate and highlight issues/constraints and mitigate.
2.
Ras Laffan Olefin Company (RLOC) a Company Operated by Qatar Chemicals; (Doha-Qatar): Aug 2018 to Aug 2020 Position: “Project Engineer- Mechanical”
Technical Work Requests (TWRs)
- 4th Cracked Gas dryer installation in RLOC - SS Internals bed installation, Piping, tie in works
- MP condensate Piping Modification
- EPC of additional C9+ Tank, associated piping, side Entry Mixers, Top-Down Mixer, civils (dyke wall, Pavement, & equipment foundations), filters, lube oil pumps, structural pipe rack, Electrical works, Instrumentation works (level Gauges/sensors, Pressure Gauges/sensors) Fire & Gas Control system, Fire Water network system extension, tie ins - in RLOC
- EPC of additional Equalization storage Tank, associated piping, civils (equipment foundations, pavement, structural racks, Electrical equipment, Instrumentation (Pressure & temp. sensors/ gauges), tie Ins- in RLOC
- EPC of 2nd Pygas Storage Tank, associated piping, tie ins, civils (Equipment & pipe support foundations), structural, Electrical, Instrumentation, Ins in RLOC
- Water Filling in to newly site erected tanks for Hydro testing from plant Fire Hydrant (C9+ , Equalization & Pygas Tanks) and Re-injection back to fire water Networks (temporary MOC) after completion of Tank Testing.
TA20 Shutdown works
- Provision of Isolation Valves in P-502 A/B Minimum Flow; Replacement of 5th Stage PRVs with Pilot Operated; HS Header Sacrificial Valve Bypass removal ;Provision of Manways (24") in Compressor (CGC) discharge Headers (by Hot Tap Process) ; Replacement of Underground Drums (D-1270 , D-1290, D-331, D-624; U-Stamp Vessels); Inlet Piping Top Take off for 41-E-201; Replacement of E-503 A/B MOVs with new Ball Valves ; Provision of Tie-in for main Fire Water Pump ;Replace Valves in Ethene Metering Skids; Replace Valve FG Metering Skids ;Replacement of Exchanger E-1210
Key Tasks and Responsibilities (but are not limited to):
- Lead / Co-ordinating with the Projects, Engineering, Process Safety, Operations ERG, ERT, EPC Contractors to the assigned multiple projects/ Tasks/MOCs/TWRs.
2. Leading / coordinating with various discipline Engineers for HAZOP Studies, Design and Detail Engineering, Materials/equipment procurements, Prefabrication / Fabrication / installation of equipment/piping testing, reinstatements, Box Ups, PSSR, Pre-commissioning & Commissioning of systems and sub-systems.
- Assisting Lead Project Engineer in all aspects of completing the assigned TWRs
- Defining clear and exhaustive scope of works for EPC, call off contracts & shut down works
5. Defining & Demarcating scope of works, roles & responsibilities, particular/special Conditions of contracts for EPC / Call off & Shutdown contractors works
- Ensuring all scopes of work are addressed, requirement of mechanical completion is well defined and agreed upon with EPC/Call off/Shut down contractor, so that there are no scope gaps or overlaps between the work-sharing offices and any subcontractors.
- Leading / Coordinating (as necessarily required) with all concerned stakeholders in provide technical supports, to resolve technical issues/ comments, liquidating punch points etc.,
- Maintaining the warranty track and resolve warranty issues if any during defect liability period
- Follow up , co-ordination & expedition of fabrication , field erection/ construction of Tanks & all associated works in RLOC Plant.
- Organizing / Participating in all walk throughs for Mechanical Completion for the assigned TWRs (of tanks, piping works and all associated E&I works, Fire and Gas Detection and Fire Fighting systems)
- Organizing / participating system wise Pre-startup safety review (PSSR) for works completed. (C9+Tanks & its associated systems and sub-systems such as mixer (Top Entry mixer, including mixer SAT- No Load Test, Part Load Test & Full Load Test) System including mixer pumps, Instrument air system, Plant air system, fuel gas system, Hydro carbon system, flare system, Fire & Gas Detection system, fire water network system, Area lighting systems, etc.,
- Participation in all Critical Review Meeting (CRT) with all concerned including with Operation, Maintenance, Process Safety, Fire & Safety, Engineering review Group (ERG) before proceeding with critical works (or next stage of works in any new system like pressure testing / Pneumatic testing / vacuum Testing of equipment, new system integration with existing systems, Hot Tapping works / Tie in works.
- Acting as a liaison between project stakeholders including third-party agencies (ERT team) and EPC subcontractors for all kind of Confined space works including Catergory-1 (the most critical CSE works) CSE works Tank inside works in construction
- Review the Project Plan along with the project planner and prepare subcontract scope packages for any work that is required to be subcontracted
15. Executing / supporting/ coordinating for other Management of Changes (MOCs) / Technical Work Requests (TWRs) being executed by peers
16. Manage/co-ordinate equipment shop fabrication, testing, packing, Transporting via sea, roads
17. Manage / co-ordinate Material procurement of Long Lead (Such as Plates, Internals, etc., accessories & Bulk Items such as Pipes, fittings, split tee, structural support materials etc.,)
18. Manage contractor, Sub Contractor claims on change to the baseline scopes/plans,
19. Coordinate and communicate effectively with Operations / Maintenance superintendents on daily basis to provide technical supports as necessarily required.
20. To prepare & perform- pre-shutdown and shut down activities
3.
Peninsular Petro-Tech Engineering WLL; (Doha-Qatar): 22nd June, 2016 to Oct 2017”
Position: “Senior Project Engineer”
Project Doha West Sewage treatment plant expansion -5: Scope includes 864 nos. Mechanical Equipment such as Smart tracks, Pumps, Compressors / Blowers, Overhead cranes, clarifiers, pressure vessels, Filter vessels, Jib cranes, Pen Stocks, Chemical Injection Skids, Air Supply Units, Mixers, Aeration nozzles, HVAC Units, Under Ground Filters, tanks, invent mixers; - Field Engineering works, erection/ installation, alignment, testing. No Load & Load Testing of equipment, plant Piping (GRP 18000 Inch Dia., Stainless Steel pipes 14000 Inch Dia. & PVC 8000 LM) Erection, testing, reinstatement, box ups, , PSSR, Pre- commissioning & commissioning assistance for Doha West Sewage Treatment Project Extension -5.
Key Tasks and Responsibilities (but are not limited to):
1. Lead the project & Construction team (consisted around 320 nos. of manpower at peak) for the assigned project;
2. Being focal point & be the accountable for all works being performed at site.
3. Authorizing the project requirements foreseen and planned for the completion of the works within the scope;
4. Preparation, implementation and maintain highest Safety and Quality standards in the Project execution / operations throughout the Project life cycle.
5. Initiating, Planning, Executing, controlling & Monitoring and closing out the projects within the stipulated time & within budget inline to the corporate strategy.
6. Overseeing day-to-day activities of the Projects at site.
7. Managing the Changes to the scope of works with client & Managing subcontractors works.
8. Monitoring compliance to applicable codes, practices, QA/QC policies, performance standards and specifications
9. Integrating all project activities for effective utilization of resources and to improve the schedule by maintaining the highest safety, Health & Environment standards
10. Reviewing construction drawings in view of constructability and ensuring availability of required materials, resources, tools etc., at site in advance.
11. Reviewing weekly targets vs status, taking appropriate action for recovery if needed
12. Preparation/ Reviewing sub-con requisition. Finalizing the requisitions for Sub-contract works, materials procurement and for Third Party Engagement as needed for the project.
13. Conducting daily walk through at site and consolidate the issues / concerns, Tracking and liquidating the issues & concerns.
14. Supporting with required resources for Site Engineers for erection of equipment, alignments, Testing, Pre-commissioning & Commissioning for System and sub-systems
15. Drafting & issuing the contractual letters to Client / contractor / sub-contractor as appliable on the issues, changes, bottlenecks concerning factors which could impact the Project objectives
16. Monitoring of site progress on daily basis
17. erection/ installation, alignment, testing. No Load & Load Testing of equipment,
18. Plant Piping (GRP 18000 Inch Dia., Stainless Steel pipes 14000 Inch Dia. & PVC 8000 LM) Erection, testing, reinstatement, box ups.
19. Participating in all PSSR as erection contractor representative,
20. Pre- commissioning & commissioning assistance within the mechanical scope.
4.
Chemie Tech Engineering LLC; (UAE-SHARJAH): 10th Oct, 2014 to June 2016”
Position: “Snr. Project Engineer”
EPC of KAFZA-II Fuel Storage Terminal (30000 Cu. M) at Basra Khor Al Zubair, Free Zone, Iraq for M/s. SKA Energy Holding Company. Project Consist of Storage Tanks and Fire Water facility, Plant piping, Gasoline Loading Pump station, Fire Water Pumps, MCC Building construction, Pump Foundations, Pump Sheds and Approx. 1100 Cu. M of concreting works, line Pipe works from Jetty to Terminal. Tie ins with existing Manifolds in Jetty.
Key Tasks and Responsibilities (but are not limited to):
- Conducting the Project Kick off Meeting with client as well Internal Dept. to discuss the salient points, Scope of the Work & Critical task in executing the Project
- Preparation, Review & Monitoring of Overall Project Macro (Level3) Schedule
- Preparation of Critical Activity Check List, review in consultation with concerned Dept. and follow up for actions & results.
- Co-ordination with Client, PMC, Sub Vendor, Contractors & Agencies.
- Engineering & Procurement Schedule (E & P Schedule) Preparation updating & follow up for delivery of the material on time.
- Preparation of Progress Measurement plan & Progress report. Review and detailed study of engineering drawings for planning and execution of Project.
- Fortnightly review of Projects major issue with higher officials and follow up for timely resolution with concerned Dept.
- Preparation of Purchase Requisitions with detailed technical delivery/ completion requirement for
- Project Sub Contracting and temporary Project Materials, tools & Tackles etc.,
- External & Internal Document Control.
- Assistance to Down Stream Depts. in terms of sharing the experience for smooth execution of Project with continual improvement.
- Preparation of draft Time extension letter, delay analysis and getting the approval from Client to get time extension. Extra claim work out for the additional work carried out and or extended stay of Compensation
- Preparation of cost escalation and getting approval from Client to raise in the invoice.
- Invoice submission for achieved progress and follow up for timely payment.
5. Arabian Industries Project LLC; (Oman-Muscat): Aug., 2011 to Sep 2014” Position: “Project Engineer -Mechanical”
Projects
1. Oman Refineries & Petrochemical (ORPIC) Turn Around 2012: Revamping of various vessels & CCR Lift Line, Cold Separator Vessel Modification Work for Oman Refineries & Petrochemical Company (ORPC) Muscat. (Refinery shut down work)
2. Engineering, Pre-Fabrication, Site Erection, Welding & Testing of 8 Nos. Water Storage Tanks of various sizes and associated Plant piping, works in Amal on Plot Steam Project.
3. Flow line Works: Design & Detail Engineering for various well head hook ups, Fabrications, testing, installation of various types of well (Water lifting, Gas injection, Gas Lifting, Steam injection) tie ins in well pads / flow lines piping’s. Hot Tapping’s works, underground / road crossings flow lines erection works. Suspended Well heads / flow lines piping dismantling
Key Tasks and Responsibilities (but are not limited to):
- Co-ordination with Worley Parson for Engineering work pertaining to the ORPIC Shutdown works & PDO Tank EPC Project
- Organizing & Participating in HAZOP Review for the proposed CCR lift line enhancements
- Consolidation of Action points raised during HAZOP Study and follow up with Worley Parson for close out / Liquidation
- Review of all P&ID, ISOs; Follow ups with Worley Parsons & PDO to get the Data sheets, purchase Specifications for Valves, Instruments etc., for submission and approval.
- Submission & Securing approvals from PDO for all engineering deliverables.
- Demarcations of Shop & field joints; Proposal with Justifications for Golden Joints
- Consolidating the materials requirement and procurement of all materials
- Prefabrication, Inspection, Testing of Pipe Spools,
- Preparation & updating of Line List
- Maintaining Line History Sheets; Performing Pre-Shutdown activities
- Preparation for Shut down activities & Performing Shutdown activities, such as cold cutting, Removal of existing 3” and replacement with 4” pipes of CCR Lift Line
- Removal & replacement of connecting Nozzles with higher sizes
- PWHT of welded joints; Reinstatement of equipment, Lines
- Carrying out the Insulations for Hot Lines
6.
Vijay Tanks & Vessels Limited; (India): June, 2006 to Aug 2010”
Position: “Trainee Engineer / Project Engineer”
- Turnkey Project: Engineering, Material Supply, Fabrication, Erection, Welding, Testing and commissioning of LPG Mounded storage Bullets of Capacity 1,500 Cu.M each 3 Nos. & 3,000 Cu.M 1No. along with its associated facilities like Truck Loading Bay system associated piping works, Control & Instrumentation system, Electrical System, Flare & Fire water networks /Fire Fighting System for M/s. Indian Oil Corporation Limited, Gujarat Refinery and M/s. IOCL Dumad Marketing Terminal Vadodara, India.
This LSTK Project covers the scope of work in the following discipline and applications as
mentioned below:
Civil works – For LPG Mounded Bullets, Dyke wall, pavement, pebble fillings, sand fillings inside mounds , Tank Truck Loading Bay , Control Rooms, Pump House,; Structural works – For temporary Barricading for Hot Work inside the Refinery, Pipe Racks, operating platforms, Lifting arrangements & HOT Systems for Valves & Equipment operation and Maintenances etc.,; Process & Utility Piping – For Mounded Bullets, Truck Loading Bays systems, Pumps & Compressors operations; Electrical works – For High Mast Tower lighting, Operation Plat form Lightings, Manual Call Point Telephonic System; Instrumentation works – For ROV operation, Bullet operations, Pump & Compressor Electronic Control; Fire Fighting Systems – For the whole mounded storage bullets with associate facilities with Water Monitor, Fire Hydrants, and Deluge Valve Systems for Water Spray System; DCS and Automation works - Integration of new facilities with existing facilities
- Design & Detail engineering, Materials Supply & Fabrication of Draft Tube Crystallizer (Shop Vessels, MOC- SA 240 Tp. 316L ) of Cap. each 50 Cu.M (4 Vessels) for Penta crystallization process to M/s. Penta Crystallizer, Saudi Arabia.
- Design & Detail Engineering, Materials Supply, Pre-Fabrication, Erection, Welding, & Testing (Hydro Static & pneumatic) Calibration of tanks (More than 50,000 MT erection weight, of 34 nos. Tanks – Various Sizes; up to 92M Ø x 20M HT) to M/s. Reliance Oil Sector Jamnagar.
- Design & Detail Engineering, material supply, pre-fabrication, Testing, & Transportations of various types of Pressure Vessels such as Mounded Bullets, Process Columns, Boilers, KO drums, Spheres etc.
- Engineering, Materials Supply & Fabrication, Testing (Hydro, Pneumatic) purging, packing, Transportation of HDT Reactor (Shop Vessel -Size 800mm ID x 14.6 m Lg) for M/s.IOCL Digboi Refinery,
- Design & Detail Engineering, Materials Procurement, Fabrication, testing & transportation of 16Nos. Skid Mounted Pig Launchers & 16 nos. Skid Mounted Pig Receivers along with associated Piping, Control and instrumentation for M/s. CAIRN ENERGY INDIA Limited.
Roles & Responsibilities (but are not limited to):
- Assisting Project Manager in all respects of the project
- Co-ordination with discipline Engineers for the Engineering work pertaining all discipline designs including Mound and all civil works, bullets, process & utility Piping, Fire detection and firefighting system
- Follow up in preparation, review and submission of plot plan, PFD, PMS, P&ID, ISOs, Data sheets, PRs & MRs and securing approvals from PMC.
- Organizing & Participating in HAZOP Review
- Consolidation of action points raised during HAZOP Study and follow up with PMC for close out / Liquidation; Co-ordinating with Third Party modelling agency for 30%,60%,90% & 100% 3D modelling & Reviews with all concerned stake holders including PMC team, end user (IOCL) operation, Maintenance, Process, Safety.
- Outsourcing scope of engineering works (structural/analysis) for the services beyond the range of VTVL
- Follow ups with Discipline Engineers & TOYO (PMC) to secure the approvals for Data sheet, purchase Specifications (PR) for critical items such as Pumps, Compressors, Equipment, Valves, Instruments.,
- Submission & Securing approvals from PMC for all engineering deliverables.
- Demarcations of Shop & field joints; Proposal with Justifications for Golden Joints
- Consolidating the materials requirement and procurement of all materials
- Visits to Suppliers/ Vendors facilities to expedite manufacturing/ FATs of Pumps, compressor, loading arms, mass flow meters, Spray nozzles, QBDs, hydrants, water monitors, Ball Valves, Gate Valves, Check valve, Globe Valves etc.,
- Mobilization of site / shop teams for Prefabrication, Erection, Inspection, Testing of Pipe Spools/equipment, Ties ins with existing systems/networks
- Preparation & updating of Line List; Maintaining Line History Sheets
- Identification of systems and sub-systems. Erection, testing of Pipe Spools (test packs), Reinstatement of equipment, Lines,
- Participating PSSR, consolidating & Tracking Punch list for close outs within the targeted schedule.
- Pre-commissioning and commissioning of systems and sub-systems